frametop

Road Refurbishment Programme

The original plan for the road refurbishment programme was expected to be completed within two months. However, once work commenced and the devastating effects of the heavy rainfall on work already completed were observed, it became obvious that continuous road maintenance would be required in order to keep the road in a condition suitable for movement of articulated dump trucks during the final bulk sample transport phase. By mid November 2006, the road had been sufficiently rehabilitated for use by the dump trucks and hauling to Koidu commenced.

Before refurbishment

Artisinal mining Artisinal mining Artisinal mining
Log bridge Log bridge
Erosion gulley in road
Artisinal mining Artisinal mining Artisinal mining
Road between Kenema and Tongo River crossing
Log bridge and flooded roadway

Work on the Tongo-Koidu road was divided into four phases. The photographs below show various stages of progress on the road and give an insight into the extent of the rehabilitation that was necessary in order to bring the road up to the standard required.

Phase 1 - 27 September 2005 to 31 January 2006

Artisinal mining Artisinal mining Artisinal mining Artisinal mining
10,656 tonnes of laterite hauled, dumped and graded to resurface Tongo-Kangama-Moimandu road Widening of the 20km Tongo-Kangama-Moimandu main road to 8-10m
Installation of 11 steel culverts - Tongo-Kangama-Moimandu road Construction of 4m x 6m x 200mm concrete bridge at Konjo

Phase 2 - 1 February 2006 to 31 March 2006

Artisinal mining Artisinal mining Artisinal mining Artisinal mining

Widening of the 20km Kangama-Moimandu-Njaima Nimikoro feeder road to 5m

Construction of 8m x 4.2m x 200mm concrete bridge at Njagbahun
Installation of 11 culverts between Kangama and Njaima Nimikoro Resurfacing of road near Moimandu

Phase 3 - 1 May 2006 to 31 January 2007

Artisinal mining Artisinal mining Artisinal mining Artisinal mining
Construction of 6m x 4m x200mm concrete bridge at Tokpombu Drilling (356 holes, 1,068m) and blasting (3,170 tonnes) of granite at Periwahun quarry
Maintenance and resurfacing of road with 16mm tailings from Koidu (4,958 tonnes) Drill and blast rock at Norway

Other activities carried out in Phase 3 included:

  • Resurfacing (4,000 tonnes of decomposed granite) and maintenance of 10km section of 5m wide road from Moimandu to Njaima Nimikoro
  • Excavation of 12,000 tonnes of waste rock for road construction at Kangama Hill Pass
  • Construction of temporary bridge at Kangama
  • Resurfacing of Moimandu-Nimikoro road for Presidential visit
  • Construction of bypass culvert at Tokpombu
  • Repair of road between Venima and Periwahun

Phase 4 - 1 February 2007 to 31 May 2007

Artisinal mining Artisinal mining
Widening from 12m to 15m from Norway Village to Moimandu Widening from 12m to 15m Moimandu to Njalehun