The development history of the Koidu Kimberlite Project from 1995 leading up to the processing of the first kimberlite from No. 1 Pipe in January 2004 is summarized below, placing in context the efforts of previous holders of the rights to the Koidu Kimberlite Project, such as Branch Energy and Energem (DiamondWorks).
 |
Jun 1995 |
Branch Energy Limited secured the rights to the Koidu Kimberlite Project. |
| Nov 1996 |
DiamondWorks Ltd acquired all the mineral assets of Branch Energy Limited, including the Koidu Kimberlite Project. |
Dec 1996
|
DiamondWorks Ltd approved funding for a bulk sampling programme at the Koidu Kimberlite Project. |
Jan 1997
|
Commencement of construction of a 20tph DMS plant and associated mining infrastructure for the bulk sampling. |
Apr 1997
|
CEMMATS Group Limited completed a Baseline Environmental Study. |
| May 1997 |
Consulting firm TERRACONSULT completed a due diligence review of project and proposed a bulk sampling programme. |
| May 1997 |
Plant ready to be commissioned. |
 |
May 1997 |
The AFRC Coup took place in Sierra Leone. Activities at the Koidu Kimberlite Project were suspended, employees were evacuated and the company maintained a skeleton staff in the country. |
| Jun 1997 |
Declaration of force majeure over Koidu Kimberlite Project. |
| Nov 1997 |
Plant and equipment was destroyed.
 |
 |
Jan 2002 |
With the return to peace in the area, Energem (DiamondWorks) management and stakeholders visited the project area to assess the damage done to the company's assets and determine what would be required to put the mine into initial commercial production. Energem (DiamondWorks) opted to wait until after the general elections in May 2002 before a decision to proceed would be made. |
| Jun 2002 |
A Joint Venture Agreement was signed between Energem (DiamondWorks) and Magma Diamond Resources (Pty) Limited for the re-development of the Koidu Kimberlite Project. Magma acquired a 50% equity stake in the Project. |
| Jul 2002 |
An Energem (DiamondWorks) management team visited Sierra Leone to conduct a preliminary study on the status of the project, and the political and security situation in the country.
A technical team which included design engineers from Bateman Minerals Ltd, a geologist, mining engineer and Energem (DiamondWorks) management conducted a site visit to undertake a detailed analysis of the technical status and requirements for the construction of a processing plant and all related infrastructure. |
| Aug 2002 |
In August 2002, Bateman Minerals (Pty) Ltd submitted a site visit report and a design proposal for the construction of the plant, crushing plant, processing plant, final recovery plant, tailings, maintenance, water supply, dewatering and electricity supply. |
| Sep 2002 |
Energem (DiamondWorks) and Magma commissioned Badger Mining and Consulting (Pty) Limited ('Badger') to undertake a conceptual mine design on the Koidu Kimberlite Project.
As part of this mandate, Badger digitally captured available historical mining and geological mapping information, and generated orebody models for the two Koidu kimberlite pipes. Badger also determined optimum production rates, considered equipment and explosives supply, determined the capital expenditure that would be required to bring the operation into production and quantified the costs involved over an initial four-year production schedule.
During the reassessment of the project, Badger was provided with historical geological and mining plans, which were mapped at different elevations, on different survey grid systems and with different geological legends. Badger standardised the maps, captured the information digitally and imported the data into SURPAC 2000 Vision mining software.
The geological contacts and existing pit outlines served as a basis for the generation of the rudimentary geological model and conceptual mine design for No. 1 Pipe and No. 2 Pipe. |
| Sep 2002 |
African Explosives Limited ('AEL') was approached to determine an initial blast design for the ore and waste material for the two kimberlite pipes. AEL took into account planned pit angles and pre-split techniques in their design, as well as parameters and assumptions specific to the kimberlite, granite and jaw crusher size. AEL also provided cost estimates which were used by DiamondWorks in their budget estimates and by Badger in their calculations of operating costs. |
| Sep 2002 |
Venmyn Rand (Pty) Limited ('Venmyn') was appointed to consolidate the historical information, review the technical and economic information contained in the various consultants' reports and to prepare an independent technical report on the Koidu Kimberlite Project. The results of the viability study were considered adequate to proceed with development of the project. |
 |
Sep 2002 - Jan 2003 |
Mobilisation of Phase 1, which included the establishment of accommodation on site and transport between Freetown and Koidu. |
| Feb 2003 |
The joint venture partners agreed to a budget of $14.5 million for the construction of a 50 tph DMS plant with associated infrastructure for development of the Koidu Kimberlite Project. Project team was mobilised and arrived on site to commence infrastructure development. |
Mar 2003 - May 2003
|
CEMMATS Group Ltd were commissioned to undertake a baseline environmental audit of the project area. |
Apr 2003
|
Gemcom Africa commenced work on a preliminary geological model based on historical data. This model formed the basis of the initial diamond drilling programme designed by Gemcom Africa and MSA Projects to delineate the geometry of No. 1 Pipe and No. 2 Pipe.
< 3D view showing planned
drillhole traces for No.1 Pipe.
|
May 2003
|
Civil engineering for plant construction commenced.
< Arrival of processing plant components
Commencement of Environmental Impact Assessment, Resettlement Action Plan, Public Disclosure and Consultation Process by Digby Wells and Associates and CEMMATS Group Ltd.
< Public meeting |
May 2003
|
Fraser Alexander completed the design and recommendations for the slimes dam. |
Jun 2003 - Nov 2003
|
Construction of 50 tph processing plant.
< View of the plant from the grizzly |
Jul 2003
|
SRK interim Open Pit Mining Study was completed. |
Aug 2003 - Oct 2003
|
Boart Longyear Inc. completed diamond drilling programme under the supervision of MSA Project's geologists.
< Diamond Drilling of No. 1 Pipe |
Oct 2003
|
SRK Consulting conducted a site visit to assess the geotechnical conditions at No. 1 Pipe and No. 2 Pipe and completed geotechnical logging of the drillhole core. |
Oct 2003
|
Submission of Environmental Impact Assessment and related studies to the Government of Sierra Leone and World Bank. |
 |
End Oct 2003
|
Construction of plant complete and commissioning began. |
14 Nov 2003
|
Final Commissioning of processing plant began - overburden from No. 1 Pipe fed through the plant. |
20 Nov 2003
|
First hard rock kimberlite from Dyke Zone B in ramp of No. 1 Pipe fed through plant.
< First kimberlite processed
|
Dec 2003 - Jan 2004
|
Plant commissioning completed. |
Jan 2004
|
Report on results of drilling programme submitted by MSA Projects. These results were handed to Gemcom Africa, who revised the preliminary geological model and calculated resource volumes for No. 1 Pipe and No 2. Pipe. |
Jan 2004
|
SRK submitted a report on the results of the geotechnical assessment and recommended pit slope angles for the open pit mine design. |
Jan 2004
|
SRK finalised the open pit mine design and produced a mining schedule. |
| Jan 2004 |
First kimberlite from No. 1 Pipe treated. |
| |
|
|